太子爷小说网 > 英语电子书 > the life of thomas telford >

第58节

the life of thomas telford-第58节

小说: the life of thomas telford 字数: 每页4000字

按键盘上方向键 ← 或 → 可快速上下翻页,按键盘上的 Enter 键可回到本书目录页,按键盘上方向键 ↑ 可回到本页顶部!
————未阅读完?加入书签已便下次继续阅读!




principle; and many were shortly after designed and erected by

Telford and other engineers in different parts of the kingdom。



Mr。 Telford continued to be consulted by the Commissioners of the

Holyhead Roads as to the completion of the last and most important

link in the line of communication between London and Holyhead;

by bridging the Straits of Menai; and at one of their meetings in

1815; shortly after the publication of his Runcorn design; the

inquiry was made whether a bridge upon the same principle was not

applicable in this particular case。  The engineer was instructed

again to examine the Straits and submit a suitable plan and

estimate; which he proceeded to do in the early part of 1818。

The site selected by him as the most favourable was that which had

been previously fixed upon for the projected cast iron bridge;

namely at Ynys…y…mochthe shores there being bold and rocky;

affording easy access and excellent foundations; while by spanning

the entire channel between the low…water lines; and the roadway

being kept uniformly 100 feet above the highest water at spring tide;

the whole of the navigable waterway would be left entirely

uninterrupted。  The distance between the centres of the supporting

pyramids was proposed to be of the then unprecedented width of 550

feet; and the height of the pyramids 53 feet above the level of the

roadway。  The main chains were to be sixteen in number; with a

deflection of 37 feet; each composed of thirty…six bars of

half…inch…square iron; so placed as to give a square of six on each

side; making the whole chain about four inches in diameter; welded

together for their whole length; secured by bucklings; and braced

round with iron wire; while the ends of these great chains were to

be secured by a mass of masonry built over stone arches between

each end of the supporting piers and the adjoining shore。  Four of

the arches were to be on the Anglesea; and three on the

Caernarvonshire side; each of them of 52 feet 6 inches span。

The roadway was to be divided; as in the Runcorn design with a

carriage way 12 feet wide on each side; and a footpath of 4 feet in

the middle。  Mr。 Telford's plan was supported by Mr。 Rennie and other

engineers of eminence; and the Select Committee of the House of Commons;

being satisfied as to its practicability; recommended Parliament to

pass a Bill and to make a grant of money to enable the work to be

carried into effect。



'Image' Outline of Menai Bridge



The necessary Act passed in the session of 1819; and Mr。 Telford

immediately proceeded to Bangor to make preparations for beginning

the works。  The first proceeding was to blast off the inequalities

of the surface of the rock called Ynys…y…moch; situated on the

western or Holyhead side of the Strait; at that time accessible

only at low water。  The object was to form an even surface upon it

for the foundation of the west main pier。  It used to be at this

point; where the Strait was narrowest; that horned cattle were

driven down; preparatory to swimming them across the channel to the

Caernarvon side; when the tide was weak and at its lowest ebb。  The

cattle were; nevertheless; often carried away; the current being

too strong for the animals to contend against it。



At the same time; a landing…quay was erected on Ynys…y…moch; which

was connected with the shore by an embankment carrying lines of

railway。  Along these; horses drew the sledges laden with stone

required for the work; the material being brought in barges from

the quarries opened at Penmon Point; on the north…eastern extremity

of the Isle of Anglesea; a little to the westward of the northern

opening of the Strait。  When the surface of the rock had been

levelled and the causeway completed; the first stone of the main

pier was laid by Mr。 W。A。 Provis; the resident engineer; on the

10th of August; 1819; but not the slightest ceremony was observed

on the occasion。



Later in the autumn; preparations were made for proceeding with the

foundations of the eastern main pier on the Bangor side of the

Strait。  After excavating the beach to a depth of 7 feet; a solid

mass of rock was reached; which served the purpose of an immoveable

foundation for the pier。  At the same; time workshops were erected;

builders; artisans; and labourers were brought together from

distant quarters; vessels and barges were purchased or built for

the special purpose of the work; a quay was constructed at Penmon

Point for loading the stones for the piers; and all the requisite

preliminary arrangements were made for proceeding with the building

operations in the ensuing spring。



A careful specification of the masonry work was drawn up; and the

contract was let to Messrs。  Stapleton and Hall; but as they did not

proceed satisfactorily; and desired to be released from the contract;

it was relet on the same terms to Mr。 John Wilson; one of Mr。 Telford's

principal contractors for mason work on the Caledonian Canal。

The building operations were begun with great vigour early in 1820。

The three arches on the Caernarvonshire side and the four on the

Anglesea side were first proceeded with。  They are of immense

magnitude; and occupied four years in construction; having been

finished late in the autumn of 1824。  These piers are 65 feet in

height from high…water line to the springing of the arches; the

span of each being 52 feet 6 inches。  The work of the main piers

also made satisfactory progress; and the masonry proceeded so

rapidly that stones could scarcely be got from the quarries in

sufficient quantity to keep the builders at work。  By the end of

June about three hundred men were employed。



The two principal piers; each 153 feet in height; upon which the

main chains of the bridge were to be suspended; were built with

great care and under rigorous inspection。  In these; as indeed in

most of the masonry of the bridge; Mr。 Telford adopted the same

practice which he had employed in his previous bridge structures;

that of leaving large void spaces; commencing above high water mark

and continuing them up perpendicularly nearly to the level of the

roadway。  〃I have elsewhere expressed my conviction;〃 he says; when

referring to the mode of constructing these piers; 〃that one of the

most important improvements which I have been able to introduce

into masonry consists in the preference of cross…walls to rubble;

in the structure of a pier; or any other edifice requiring strength。

Every stone and joint in such walls is open to inspection in the

progress of the work; and even afterwards; if necessary; but a

solid filling of rubble conceals itself; and may be little better

than a heap of rubbish confined by side walls。〃  The walls of these

main piers were built from within as well as from without all the

way up; and the inside was as carefully and closely cemented with

mortar as the external face。  Thus the whole pier was bound firmly

together; and the utmost strength given; while the weight of the

superstructure upon the lower parts of the work was reduced to its

minimum。



'Image' Section of Main Pier



Over the main piers; the small arches intended for the roadways

were constructed; each being 15 feet to the springing of the arch;

and 9 feet wide。  Upon these arches the masonry was carried

upwards; in a tapering form; to a height of 53 feet above the

level of the road。  As these piers were to carry the immense weight

of the suspension chains; great pains were taken with their

construction; and all the stones; from top to bottom; were firmly

bound together with iron dowels to prevent the possibility of their

being separated or bulged by the immense pressure they had to

withstand。



The most important point in the execution of the details of the

bridge; where the engineer had no past experience to guide him; was

in the designing and fixing of the wrought iron work。  Mr。 Telford

had continued his experiments as to the tenacity of bar iron; until

he had obtained several hundred distinct tests; and at length;

after the most mature delilberation; the patterns and dimensions

were finally arranged by him; and the contract for the manufacture

of the whole was let to Mr。 Hazeldean; of Shrewsbury; in the year

1820。  The iron was to be of the best Shropshire; drawn at Upton

forge; and finished and proved at the works; under the inspection

of a person appointed by the engineer。



'Image' Cut showing fixing of the chains in the rock



The mode by which the land ends of these enormous suspension chains

were rooted to the solid ground on either side of the Strait; was

remarkably ingenious and effective。  Three oblique tunnels were made

by blasting the rock on the Anglesea side; they were each about six

feet in diameter; the excavations being carried down an inclined

plane to the depth of about twenty yards。  A considerable width of

rock lay between each tunnel; but at the bottom they were all


返回目录 上一页 下一页 回到顶部 0 0

你可能喜欢的